‹header›
‹date/time›
Click to edit Master text styles
Second level
Third level
Fourth level
Fifth level
‹footer›
‹#›
Background:  During the Project Development Cycle there is a Planning Phase and a Construction Phase.  Part #2 of the module covers the basics of how to develop the As-Planned S-Curves during the planning phase.  Part #2 covers the Development of the As-Built S-Curves during the construction phase.  Part #3 Covers how to determine Job Status during the construction phase using both sets of curves.  Part #3 also covers interpretation of the results.
Reading Assignment:  Halpin and Woodhead, Chapters 2, 6, 12, and 14.
This Part should take 20-30 minutes to cover in detail, depending upon the level of experience of the students. This timing assumes that students are somewhat familiar with the estimating and scheduling process.  You could shorten the time by leaving ou the exercises.
These constitute the teaching objectives.
These Learning Objectives could make excellent pop questions.  However, I usually ask Exam questions around the complete set and not the As-Planned set.
Theoretically, S-Curves can be used to control the planning phase as well as the construction phase of the process.  As a matter of practice it is rarely done.  That is not to say that on mega projects it would not be a good idea.
I often use this example project in the design of hour exams and finals.
In-class surveys have shown that very few of today’s students have any degree of familiarity with construction of any type. They will be unfamiliar with most of these common road construction terms. So, it will be necessary to go over them in some detail.
Base Material:  In Central Texas it is generally crushed and graded limestone material from one of the Quarries along the Balcones Escarpment. It is generally put on top of the sub-base in 12-inch lifts and compacted to optimum density using a variety of compaction equipment. It is the load bearing structure. Shoot and Chip: Texas practice is to shoot a thin asphalt layer on top of the compacted base course and then spread a layer of chips (pea gravel) over that.  This is the wearing surface. Pea Gravel: Is a manufactured, gap graded (.25” to .50”) gravel with most of the fines removed. It can be hard limestone or river gravel. Limestone is preferred because of polishing. Design Profile: The design life of a rural FM Road in Texas is normally 4-years. At that time a shoot and chip seal coat is applied after any major break-up of the base material is repaired. At the end of 7-years the pavement condition is assessed. And the road is resealed or rebuilt as required.  Light traffic roads in West Texas seldom need rebuilding.  Roads in the fat-clay regions of central and east Texas require constant maintenance because of failure of the sub-base. This causes structural failure of the base course, etc.  It would cost $-billions to build FM-Roads to any other design profile.  High volume roads are built to higher standards.
This is an example of sequential tasking.
1.The base can not be applied until the sub-base is prepared.
2. A section of road can not be paved until the base is prepared. 
Some over-lap can be tolerated. For example, the base usually cures a day before it is paved. To avoid start and stop operations (they are expensive) the contractor will wait until the base is almost complete before starting  paving operations.
Section 12.9 in Halpin has some good examples of breaking a project into work packages.  In is good practice to use the Means Manual as a guide.
The actual answer is not as important as getting the students to think about the process hauling the base material to the site, grading and shaping the dumped material, and then compacting it to proper density.
There is a lot of busy work on this slide. The schedule information is on the top.  This typically comes from any planning software like Primavera or Project.  Resource allocation and costing can also result from running one of the industry standard software suites. This is an example using Excel to display the required operations.
1. The Bar Chart shows which tasks are active on which days and the daily cost rates.
2. The cost per day can be computed directly.  The %/day follows.
3. The total work per day is not easy to obtain.  For planning purposes, you could assume that work is a function of cost as modified by some weighting factor.  In this case we assumed that they were independent. 
In construction, volumes of bulk materials are measured in cubic yards, areas in square yards or square feet, linear (or running) measurements are in feet and miles.  This is a good opportunity to make sure everyone remembers the conversions and how to use them.
In the estimating module you actually use all of this but since that occurs prior to construction this is simply a review.
These data were taken from the bottom of the Bar-Chart slide and displayed vertically.
If we assume that cost and work are only loosely related, you should not be surprised to see cost and work only loosely related.
This shows the correct way to plot the data from the table in the previous slide. At this point there is not much to say about the curves.
The different scales are important; so, make an issue of it.  It will become obvious when we plot the As-Built Curves in the next Part.
You will need to furnish a some graph paper for this exercise. Engineering paper will do.  DO NOT hand out a template. Have the students plot from scratch.
This does not make a good Exam problem.

Related Links:

Togel178

Pedetogel

Sabatoto

Togel279

Togel158

Colok178

Novaslot88

Lain-Lain

Partner Links