S-curve Modules
 

S-curve Modules

  • Introduction
    This module illustrate how to develop a set of As- Planned S-Curves from scheduling information and estimates, developed sometime before actual construction operations begin. It also reviews the conceptual design estimating process to the extent necessary to set the context.
  • Instructional Objectives
    • Be able to construct an As-Planned schedule of work and cost versus elapsed time from a typical (but simplified) construction project Gantt Chart
    • Be able to plot and identify the As-Planned S-Curves best representing these schedules
    • Be able to construct a schedule of work and cost versus elapsed time from a typical (but simplified) set of observed field data
    • Be able to plot and identify the As-Built S-Curves best representing these schedules
    • With respect to chart layout, be able to label all curves and axes
    • Given a set of S-Curves, be able to determine Cost Variance, Schedule Variance, Budget Variance
  • Student Materials
    Please select the desired format from among these:
  • Instructor guide
    Word
  • S-Curve Module Examples
    Excel
  • S-Curve Exam Questions
    Word

 

 

 

 